Weekly Road Report

Rickard Road

For the Week of September 19 to September 25, 2021

 

  • Rickard Road: Groff Rd to US-20 Improvement (Bend Area) – Installation of fencing and permanent signage will be occurring between Gosney Road and US-20. Rickard Road remains closed from the end of existing pavement east of Bozeman Trail to US 20. A designated detour route is in place via Gosney Road for access to and from US-20. Residents living on Rickard Road within the closure will have access during construction.
     
  • NE Negus Way and NE 17th St Improvement (Redmond Area) – No work will be occurring this week. Work will resume the week of September 26.
     
  • Paving of Cottonwood Road: US-97 to BNSF RR (Sunriver Area) – Pavement rehabilitation work will be occurring between US-97 and the BNSF railroad bridge.  Work will include removal and replacement of existing pavement, installation of roadside delineators, and pavement striping. Road users should anticipate single lane closures facilitated by flaggers and delays of up to 20 minutes during work hours.  Work hours are 7 a.m. to 6 p.m., Monday through Friday (excluding holidays).

For more information, please contact the  Deschutes County Road Department at (541) 388-6581

News Release Issued: September 17, 2021