NW Lower Bridge Way / 43rd Street Intersection Improvement Project
NEWS
The Virtual Open House has closed. Members of the public can continue to view the Virtual Open House materials at: www.deschutes.org/LBW_43rd
Additional project documents are available under "Supporting Documents" below. A summary of the community feedback from the Virtual Open House is also available under “Supporting Documents”.
The next steps in the Project development are as follows:
- Advance design of preferred improvement alternative (Roundabout concept)
- Conduct environmental assessment and obtain necessary clearances for right-of-way acquisition
PURPOSE AND NEED
NW Lower Bridge Way is an east-west rural collector connecting the area west of Terrebonne to US 97. NW 43rd Street is a major collector and serves as the primary access route for more than 5,000 residents of Crooked River Ranch. NW 43rd Street intersects NW Lower Bridge Way at a three-legged intersection with stop sign control on the north leg only, where there has been a history of crashes. The intersection is a primary node for both recreational and residential traffic, and is bisected by the Sisters to Smith Rock Scenic Bikeway.
The NW Lower Bridge Way/NW 43rd St Intersection Improvement project is identified in the County’s 2020-2040 Transportation System Plan as a high-priority project.
SCOPE OF WORK
The Project scope includes:
- Conducting a safety and capacity analysis at the intersection of NW Lower Bridge Way / NW 43rd Street
- Revising intersection geometry to improve safety for vehicular and bicycle traffic
- Installing new pavement markings and signage
ESTIMATED COST AND SCHEDULE
The current estimated project cost is $2.8 million
Anticipated project schedule:
- Preliminary Engineering: July 2023 – December 2024
- Right-of-Way: June 2024 - December 2024
- Construction: January 2025 – September 2025
Current project exhibits are available under “Supporting Documents” below.