Weekly Road Construction Update Week of March 24 to March 29

This week’s photo shows construction progress at the Smith Rock Way Bridge.

Powell Butte Highway/Butler Market Road Intersection Improvement (Bend Area) – Temporary sign installations will be occurring near the intersection of Powell Butte Highway and Butler Market Road.  

Traffic Information – Shoulder closures will be occurring along Powell Butte Highway and Butler Market Road. Road users should exercise caution. Butler Market Road will be closed to traffic between Powell Butte Highway and Dickey Road starting on April 1. A designated detour route will be in place via Nelson Road and Dickey Road. 

Smith Rock Way Bridge Replacement (Terrebonne Area) – Bridge foundation work will be occurring at the Smith Rock Way Bridge. 

Traffic Information – Smith Rock Way remains closed to through traffic between NE 33rd Street and Lambert Road for bridge replacement work. A designated detour route is in place via Lambert Rd, NE Wilcox Avenue and NE 33rd Street. Access for local traffic will be maintained during construction. Work hours are 7 a.m. to 6 p.m., Monday through Friday. 

Hunnell Road: Loco Road to Tumalo Road Improvement (Bend Area) – Grading work will be occurring on Hunnell Road between Pohaku Road and Tumalo Road, as well as between Bowery Lane and Rogers Road.  

Traffic Information – Hunnell Road remains closed to through traffic between Pohaku Road and Tumalo Road. Access for local traffic will be maintained during construction. Hunnell Road is also closed between Bowery Lane and Rogers Road for grading work. Local residents should access Bowery Lane from US-97. Work hours are 7 a.m. to 6 p.m., Monday through Friday. 

Gribbling Rd Bridge Replacement (Bend Area) – Paving work will be occurring on Gribbling Road near the Central Oregon Irrigation Canal. 

Traffic Information – Gribbling Road remains closed to traffic at the Central Oregon Irrigation Canal for bridge replacement work. A designated detour route is in place via US-20, Gosney Road and Ward Rd. Access for local traffic will be maintained during construction. Work hours are 7 a.m. to 6 p.m., Monday through Friday. 

Burgess Road Utility Work (La Pine Area) – Utility work will be occurring along Burgess Road near the intersection with Glenwood Road.  

Traffic Information – Shoulder closures and single-lane closures facilitated by flaggers will be occurring on Burgess Road. Road users should exercise caution and expect delays of up to 20 minutes during work hours. 

*** Work hours are subject to change based on weather conditions. *** 

FOR MORE INFORMATION 

Visit: deschutescounty.gov or TripCheck.com 

Contact: Deschutes County Road Department at (541) 388-6581 

News Release Issued: March 22, 2024