Onsite Inspections
Notice
- Upload your As-Built via Oregon ePermitting prior to scheduling a Final Inspection. OAR 340.071.0170(3)
- ATT, sand filters and pressure distribution systems will need to provide a start up inspection report prior to issuing Certificate of Satisfactory Completion.
- Incomplete work will result in additional inspection fees, ensure that the work being inspected is complete prior to scheduling inspections.
- For safety of our staff, all pets must be put in a separate area from Inspectors.
- Gate code information must be included in inspection notes, if applicable.
- The following inspections should only be scheduled if you are completely ready, if there are circumstances where you need a partial inspection, reach out to septic@deschutes.org for further instructions.
Onsite Wastewater System Inspection List
Standard System
- Schedule a Pre-Cover inspection (#7020) prior to backfilling. Staff will be inspecting the following items:
- Septic Tank Inspection
- Tank Water Tightness Test
- Effluent Line Inspection
- Drainfield Inspection
- Upload your As-Built via Oregon Epermitting prior to scheduling a Final Inspection.
- Schedule a Final inspection (#7999)
Capping Fill System
- Schedule an Initial Capping Fill inspection (#7810) prior to installing the drainfield cap. Staff will be inspecting the following items:
- Cap Material Inspection
- Septic Tank Inspection
- Tank Water Tightness Test
- Pressure or Effluent Line Inspection
- Scarification
- Drainfield Inspection
- Schedule a Secondary Capping Fill inspection (#7830) after the drainfield cap is installed.
- Upload your As-Built via Oregon Epermitting prior to scheduling a Final Inspection.
- Schedule a Final inspection (#7999). It will include erosion control establishment.
Pressure Distribution System
- Schedule a Pressure Distribution inspection (#7590) once the distribution laterals are installed. Staff will be inspecting the following items:
- Septic Tank Inspection
- Effluent Line Inspection
- Drainfield Inspection
- Schedule a Squirt Test inspection (#7030) prior to installing the top layer of drain media. Staff will be inspecting the following items:
- Tank Water Tightness Test
- Pump/Alarm System
- Upload your As-Built via Oregon Epermitting prior to scheduling a Final Inspection.
- Schedule a Final inspection (#7999)
Sand Filter System
- Schedule an Initial Sand Filter inspection (#7230) prior to installing sand media. You may have gravel in the box. Staff will be inspecting the following items:
- Scarification
- Sand Filter Liner/Box
- Schedule a Secondary Sand Filter inspection (#7240) prior to installing the drain media/underdrain media.
- Schedule a Squirt Test inspection (#7030) prior to installing the top layer of drain media. Staff will be inspecting the following items:
- Septic Tank Inspection
- Tank Water Tightness Test
- Pressure or Effluent Line Inspection
- Pump/Alarm System
- Schedule a Sand Filter Cover inspection (#7250) to inspect the drain media cover and filter fabric.
- Upload your As-Built via Oregon Epermitting prior to scheduling a Final Inspection.
- Schedule a Final inspection (#7999) to inspect the backfill.
Additional ATT Inspections
- Schedule an Initial Advanced Treatment Technology inspection (#7710) for ATT installations.
- This inspection is typically combined with a Pre-Cover inspection (#7020) or Squirt Test inspection (#7030).
- Schedule a Final inspection (#7999)