To expedite this process, make sure that the following are completed before submitting your Certificate of Occupancy Request:
- All related permits, including temporary power, driveway access, and septic installation have approved final inspections or Certificate of Satisfactory Completion (if applicable)
- Final Planning and Infrastructure approval from City of La Pine or City of Sisters if New Dwelling is constructed in their jurisdictions
- System Development Charge (SDC Fees) must be paid in full
- SDC fees are due for replacement dwellings if the original dwelling was removed more than 2 years prior to final inspection on replacement dwelling
- All Final Building, Plumbing, Electrical and Mechanical inspections approved
The following requirements will be met once you complete these items in the request form:
- Insulation Certificate added to the permit record
- All Contractors verified
Requirements for Commercial Certificate of Occupancy
- All Conditions of Approval for Building and Planning must be met. You can find Structural Permit conditions in the documents section of the Commercial Structural Permit.
- Third Party Inspection reports must be uploaded to the permit when applicable. Please refer to Special Inspection Agreement for third party inspection requirements.
- Related Supplemental Mechanical, Electrical and Plumbing permits must have approved final inspections.
- Final Building inspection must be approved
- System Development Charge (SDC Fees) must be paid in full.